{"id":6859,"date":"2024-05-30T13:30:13","date_gmt":"2024-05-30T13:30:13","guid":{"rendered":"https:\/\/www.van-elle.co.uk\/?p=6859"},"modified":"2024-05-30T13:30:14","modified_gmt":"2024-05-30T13:30:14","slug":"completion-of-king-post-retaining-wall-project","status":"publish","type":"post","link":"https:\/\/www.van-elle.co.uk\/2024\/05\/30\/completion-of-king-post-retaining-wall-project\/","title":{"rendered":"Completion of King Post Retaining Wall Project at NEAR M1 J33"},"content":{"rendered":"\n

Van Elle’s Specialist Piling division has completed the installation of a king post retaining wall at the NEAR M1 J33 site.<\/p>\n\n\n\n

Contracted by Costain Group PLC<\/a> as part of the National Highways M1 National Emergency Area RetroFit scheme<\/a>, we installed 130m of king post wall to support the construction of a new Emergency Refuge Area.<\/p>\n\n\n\n

The project involved installing 65No piles, each measuring 900mm in diameter and spanning between 7 to 9.5 meters in depth with beam heights between 10m and 12.5m.<\/p>\n\n\n\n

In addition to the piling work, our team managed all associated earthworks, panel installations and logistics, ensuring comprehensive project delivery in a confined working area next to the live motorway.<\/p>\n\n\n\n

We utilised our fleet of specialised equipment, including the lorry-mounted STM20 for the construction of the wall.<\/p>\n\n\n\n

The intricacies of the wall design, characterised by its multiple levels and directional changes, presented notable construction challenges.<\/p>\n\n\n\n

Despite obstacles such as restricted access and navigating overhead services, our dedicated team completed the project to programme.<\/p>\n\n\n\n

For more information on our complete range of temporary and permanent retaining structure solutions click here.<\/a><\/p>\n\n\n\n

\n
\n
\n